Date19/07/2024
Submitted ByM Faizan Bangash
Today Activities

1. A webmail account has been created for AGMUP.
2. A meeting was conducted with the CEO, IT team and Iqbal.
3. The supply chain network printer has been installed and shared with all connected computers.
4. The electrical work for Unit 1 has been completed as advised by the CEO.
5. The sound system and amplifier issue in Unit 10 will be resolved within two working days.
6. An in-depth discussion was held with Kashif, GMSCM and the IT team regarding the implementation plan for the ERP system.

Next Day Activities

1. A visit was made to the Warsak Road Branch (U-3) in Peshawar for electrical work.
2. A visit was made to the Charsadda Road Branch (U-10) in Peshawar for electrical work.
3. A meeting was held with top management to discuss the ERP system.

Report Overview

Request for a Meeting Regarding the ERP System

ReplyWhatsApp Message Sender