| Date | 30/09/2024 |
|---|---|
| Submitted By | noor ul |
| U-1 | Reports nott shared ( Daily base call karta hu but noman sab nai samjne wale ) |
| U-2 | No major issue |
| U-3 | Stock not received due to supply chain ledger but issue was resolved by P.manager |
| U-4 | 5 demand is pending ( complete will be tomorrow morning) |
| U-5 | Expiry clearance |
| U-6 | 2 demands is pending ( short) |
| U-7 | 2 Demnad is pending ( local ) |
| U-8 | No issue |
| Report Overview | Procurement Manager 1️⃣Today's reports verified that 75 items were zero but the order is shared with the supply chain, some items will be removed soon. 2️⃣Nizam and ptepup System Expiry issue is running which I have cleared 3️⃣Has asked Hubab to separate the short item list of verifications of the NA head 4️⃣Follow up the running items and increase the daily basis of three to four boxes 5️⃣ |
| Reply |