| Date | 21/11/2024 |
|---|---|
| Submitted By | noor ul |
| U-1 | Expiry clearance |
| U-2 | 1 Demnad is pending ( short) |
| U-3 | No issue are found |
| U-4 | 1 Demnad is pending ( local) |
| U-5 | Special task working in progress |
| U-6 | 2 Demnad is pending ( imp) |
| U-7 | 2 Demnad is pending ( local and short) |
| U-10 | No issue |
| Report Overview | 🛑Tomorrow Activities Fully focused on fresh Expiry 🛑Today Activities 1️⃣Finalize the partial payment schedule and collection days 🛑U2 working in progress |
| Reply |