| Date | 09/08/2024 |
|---|---|
| Submitted By | noor ul |
| U-1 | Report not shared as per CEO arranged the meeting but Noman on leave that's why meetings is pending |
| U-2 | ⬛5 demand is pending ( The item order has been delivered to the company) |
| U-3 | ⬛Expiry clearance |
| U-4 | 2 demand is pending ( the item order has been delivered to the company) |
| U-5 | ⬛1 demand is pending ( item is short) |
| U-6 | ⬛6 demand is pending ( 3 demand was completed from U3 rest of item is local ) |
| U-7 | ⬛Running stock is less and order shared with supply chain and stock was pending reaosn is huge amount ledger ( p manager with discuss let see ) |
| U-8 | ⬛Report is not stisfactory ( Tomorrow visit will be plan for tomorrow then guided in detail) |
| Report Overview | Procurement manager 1️⃣Weekly rejects verified at U5 with mostly zero items but orders have gone to some companies and some will be placed. 2️⃣Running items in Shelf wise are slightly reduced and will be working on those highlighted for rewards 3️⃣. Expiry of drugAgency & Muller and Udl is pending, which will be cleared this Monday, God willing. 4️⃣The seven month intimations are so much that I asked Inam bhai to start working on it. Yesterday issue were pending |
| Reply |